Brakes Auto India Ltd has informed BSE that the Company at Nardana, Dhulia, is developing an Integrated Project. However due to non-availability of water and power, the Company’s project is delayed for further 8 to 9 months. MIDC has brought from 35km and the Company’s power connection was given by a small feeder (for constructional work) that was not capable to meet Company’s requirement. Nardhana industrial water was supplied from the river that dried up and the water was not available therefore MIDC and Govt. of Maharashtra made permanent arrangement for water and power as under.